Math 533 Course Project Part A Anti Essay

Conveyor Belt Project
Part 2
1. When is the project estimated to be completed? How long will the project take?
The project is estimated to be completed on 02/02/2012. The project will 530 days.

2. What is the critical path(s) for the project?
There’s only one critical path:
Architectural decisions - Hardware specifications - Hardware design - Hardware documentation - Integration first phase - Serial I/O drivers - System hard/software test - Network interface - Integrated acceptance testing.

3. Which activity has the greatest amount of slack?
The activity of “Utilities documentation” has the greatest amount of slack with 115 days.

4. How sensitive is this network?
In general, the more number of critical paths, the higher the sensitivity in a project. Since the particular network has only one critical path, the network is not a very sensitive.

5. Identify two sensible milestones and explain your choices.
The two sensible milestones are “Integration first phase” and “System hard/software test”. “Integration first phase” is the merged activity with the highest number of precedence; there are seven activities precede (merge) the activity of “Integration first phase”. “System hard/software test” is burst activity with the highest number succession; there are four activities succeed (burst) the activity of “System hard/software test”.

6. Compare the advantages/disadvantages of displaying the schedule as a network versus a Gantt chart.
In a project summary/work, network diagram and Gantt chart could be used to display specific features of the complexity and dependencies of the project activities. The network diagram shows logical relationship/sequence and the dependencies among the various activities that take place within a project using chronological flow from start to finish. It shows how the various activities flow from start to finish and could identify the critical path for the project. However, a network diagram does not reflect the...

Show More

Reform Movements: Part B Essay

724 WordsNov 5th, 20133 Pages

List several evils that the reformers of the period 1820-1860 tried to eliminate. Gender inequality and slavery were the two biggest evils that reformers tried eliminating in the time period. The abolition of slavery had many reformers behind it. Two very important men trying to achieve this were Frederick Douglass and William Lloyd Garrison, a white man, going to show there was support from all types of people. Two of the women’s rights advocates were Elizabeth Cady Stanton and Sarah Grimke. They both achieved great things to help out their cause. Although slavery and gender equality are arguably the most important evils in the time period there were still many other. One of these was alcohol. During the time period the Temperance…show more content…

Going along with this the reformers actually sort of worked together to achieve their goals. Many people were advocated for two or more of the movements and others at least agreed with or supported the other reformers. Something else that tied these people together was their use of nonviolence. Of course there are a few exceptions, but most of the reformers followed this principle. Lastly, all reformers sought after the common goal of ridding their lives of immorality. Everything the reformers wanted to get rid of was seen by them as immoral. All wanted a Utopian society.

Would you consider these individuals as idealists or practical reformers? I consider most of the abolitionists to be idealistic. Although it would be different on a case to case basis, this applies to the reformers in general. This is due to the fact that all of the reformers wanted to reach their goal then. In reality it would take many years to fully achieve what they wanted. There was no compromising with the reformers. They didn’t just want some reforming; they wanted corruption to be completely eradicated. This lack of compromise is what classifies the reformers as idealistic. That is the distinguishing feature between idealistic and practical reformers.

To what extent did these reformers achieve success in the period 1820-1860? During the time period, the reformers weren’t very

Show More

Categories: 1

0 Replies to “Math 533 Course Project Part A Anti Essay”

Leave a comment

L'indirizzo email non verrà pubblicato. I campi obbligatori sono contrassegnati *